Loading...
Loading...

Client
Mid-Sized Manufacturing Conglomerate (hypothetical)
Date
Mar 05, 2026
Timeline
16 weeks
Identified ₹412 crore of EBITDA improvement (8.4% of revenue), of which ₹236 crore was executed in 14 months — restoring the client’s covenant headroom and funding a greenfield plant.
A ₹4,900 crore diversified manufacturer (auto components + industrial fasteners) was facing a perfect storm: raw material inflation of 14%, a customer demanding 6% annual price-downs, and EBITDA margin that had slipped from 11.2% to 7.8% in three years. The bank's covenant required an 8% margin by fiscal year-end — 11 months away. The client's own cost-reduction program ("Project Lean 2.0") had delivered only ₹28 crore in 18 months against a ₹200 crore target.
The CFO's question: "Where is the money actually hiding, and can we get it in time?" The board wanted a Big-4-grade, evidence-based transformation — not another poster campaign.
We ran a 16-week cost transformation using a "cost-to-serve + zero-based" hybrid methodology, with five value workstreams:
Each workstream had a dedicated sprint team with plant-level data collectors; we tracked weekly "value captured" against a rigorous benefits register with owner, date, and verification method.
Procurement was the single biggest pool. Should-cost modelling showed the company was paying 9–17% above best-in-class on 12 of 28 categories — largely due to fragmented buying (4 plants buying independently, 3,400 suppliers for ₹2,100 crore of spend). Consolidating 60% of spend with 120 preferred suppliers unlocked ₹96 crore.
OEE hid a 23% capacity illusion. Three plants ran below 55% OEE; the binding constraint was changeover time (average 74 minutes vs. 22-minute benchmark) and unplanned downtime. Shift-pattern and changeover-SMED programs unlocked the equivalent of a free shift at two plants — ₹74 crore of avoided capex and ₹41 crore of conversion-cost savings.
ZBB found the "creep." ₹93 crore of opex was discretionary spend that had become structural — including ₹11 crore of third-party logistics for inter-plant transfers that an internal milk-run design eliminated.
Inventory days of 68 vs. 46 benchmark trapped ₹87 crore of cash; safety-stock recalibration alone released ₹52 crore without a stockout risk above 0.3%.
We recommended a three-wave execution plan:
Non-negotiables: a benefits register audited quarterly by internal audit; a "no cost-cuts without process change" rule to avoid the bounce-back effect; and a transparent communication plan to protect employee morale — the #1 failure mode in transformations of this scale.
Within 14 months, the client banked ₹236 crore of the ₹412 crore identified (57% of the total), restoring the 8% covenant with ₹61 crore of headroom. Procurement savings alone funded the ₹85 crore greenfield plant the board had shelved a year earlier. Two years on, the ZBB cadence is embedded in the annual cycle, and the EBITDA margin holds at 9.1% — above the pre-decline peak — with the benefits register showing no material leakage.
Case study reconstructed for illustration from typical engagement patterns. Client and figures are hypothetical.